Solution Provided | Gas Bottle Storage Facility
Discipline | Mechanical, Civil and Electrical Engineering
The client required a new Dangerous Goods (DG) Bottle Gas Storage Facility due to concerns of their existing facility failing to comply with safety regulations.
Carnac-Project Delivery Services (Carnac) managed, designed and constructed a new gas bottle storage facility and modified the existing facility. Carnac produced the facility from concept to handover.
The gas facility requirements were:
- Stocks of bottled gas must be easily rotatable;
- Ensure full compliance with the standards and regulations;
- Improve manual handling of product to ensure safety risks are minimised; and
- Plan for full and empty bottle storage to comply with the Australian Standards and improved the delivery processes.
Carnac delivered a detailed design of the project, consulting the client throughout the process.
The construction phase included the:
- Procurement of all mechanical, electrical and structural elements required for the construction;
- Civil site works, concrete and asphalt installations;
- Structural steel fabrication and erection;
- Electrical installation; and
- Structural, Mechanical and E&I completion check list.
Carnac delivered a high quality Gas Storage Facility, remaining within a fixed price cost. A Manufacturers Data Report (MDR) was also prepared by Carnac and handed over to the client.